Project Overview

  • Installation of milk pre-cooling and storage systems for 80,000L/Day
  • 10 Farms each farm has 2 milking parlors that have a 40,000L/Day pre-cooling and storage systems
  • Calibration with Afimilk
  • The system of 40,000L/Day included:
    • 2x500L balance tanks
    • Milk filtration system
    • 3,000L/H PHE for cooling the milkfrom 26°c to 4°c
    • 2x 22,000L insulated milk storage tanks
    • CIP System for washing the balance tanks and the storage tanks
    • Water chiller at 0°c for cooling the milk
    • System control panel

Scope of Project:

  • Planning
  • In house manufacturing of dairy components and equipment
  • Installation and Commissioning
  • Training (Technical, Technological)
  • After Sales Support